How Long Does Council Approval Take in Sydney? Council-by-Council DA Timelines (2026)

Share on

November 1, 2026

If you are asking how long does council approval take Sydney owners should plan for, the honest answer is “it depends on your council, and the gap between councils is large.” The NSW Planning Portal’s September 2026 council league table, as of 9 October 2026, shows average assessment times ranging from 41 days in Campbelltown to 122 days in Blacktown. For a knock down rebuild, that difference can decide how many months you pay rent and interest before the excavator arrives.

This guide sets out the numbers, explains what they do and do not tell you, and shows how to shorten your own approval timeline.

How Long Does Council Approval Take Sydney Councils to Deliver? The Targets

The NSW Government’s Statement of Expectations Order asks councils to determine development applications as soon as practical, and within the lower of their previous financial year’s average or these averages from lodgement:

  • 90 days from 1 July 2026 to 30 June 2027
  • 80 days from 1 July 2027 to 30 June 2028
  • 65 days from 1 July 2028

Councils are also expected to lodge applications within an average of 7 days of submission. Statewide, average assessment times fell from 115 days to 84 days as of 31 May 2026. Councils averaging 90 days or more, or with 60% or fewer applications meeting the expected timeframe, can be flagged for intervention.

Council by Council: September 2026 Snapshot

The chart below shows average assessment days for Greater Sydney councils from the Planning Portal league table (September 2026 snapshot, as of 9 October 2026).

how long does council approval take sydney

How long does council approval take sydney: horizontal bar chart of average DA assessment days by Sydney council, September 2026 snapshot: Campbelltown 41, Camden 45, Sydney 53, Strathfield 61, Waverley 63, Wollondilly 67, Lane Cove 68, Georges River 69, Randwick 71, Willoughby 74, Burwood 74, Bayside 75, Canada Bay 76, Fairfield 77, Canterbury-Bankstown 77, Hawkesbury 78, Northern Beaches 78, Mosman 80, Ku-ring-gai 84, Sutherland 85, Ryde 87, The Hills 87, North Sydney 87, Blue Mountains 89, Cumberland 91, Parramatta 94, Hornsby 96, Inner West 96, Woollahra 99, Penrith 114, Liverpool 118, Hunters Hill 120, Blacktown 122

A few patterns stand out:

  • Fastest averages: Campbelltown (41), Camden (45), Sydney (53), Strathfield (61) and Waverley (63).
  • North Shore and northern suburbs: Mosman 80, Willoughby 74, Ku-ring-gai 84, North Sydney 87, Hornsby 96, Hunters Hill 120.
  • South: Georges River 69, Sutherland 85.
  • Western Sydney: wide spread, from Campbelltown (41) to Blacktown (122), with Penrith (114) and Liverpool (118) among the slower averages.

How to Read These Numbers Carefully

They are averages across all DA types. A council’s figure includes everything from pools and signs to larger developments. A simple, complete knock down rebuild application may be faster than the average. A complex or non-compliant one may be slower.

They are gross days. The league table counts calendar days from lodgement to determination, and does not deduct stop-the-clock periods when council is waiting for you to supply information. The Planning Department states that withdrawals, modifications and s8.2 reviews are excluded.

They show the past, not a promise. Council workloads, staffing and policy change month to month.

They exclude work before lodgement. Design, surveys, reports and pre-lodgement discussions all come before the clock starts.

Lodgement time is separate. The league table also shows average lodgement days, which range from about 2 to 23 days across Greater Sydney councils.

DA vs CDC: A Different Clock

If your site and design qualify, a complying development certificate (CDC) can be issued by a private certifier or council without a merit-based DA. A CDC is not subject to the DA assessment averages above. Eligibility depends on lot size, zoning, setbacks, height, overlays and other fixed standards. Read block suitability for a knock down rebuild to check whether CDC is realistic for you.

Where the Time Actually Goes in a Rebuild Approval

For a typical knock down rebuild, approval is one part of a longer program. Our knock down rebuild timeline breaks down design and approval as often the longest single stage, with several months commonly spent before demolition starts. The council assessment period sits inside that.

Typical time drivers include:

  1. Design and documentation. Surveys, geotechnical reports, BASIX, architectural drawings and consultant reports.
  2. Pre-lodgement checks. Heritage, flooding, bushfire and tree controls.
  3. Council’s lodgement review. Some councils take longer to accept an application as complete.
  4. Assessment. Includes referrals and any requests for information.
  5. Determination and conditions. Then comes the construction certificate.

What Has Changed in 2026

Notification. Since 1 September 2026, the statewide Community Participation Plan excludes many low-impact developments, including dwellings up to two storeys, from formal neighbour notification if no height or floor space ratio variation is needed. That may reduce one step for some projects. See NSW Community Participation Plan 2026.

Targets. Councils now work to a Government target of an average of 90 days, falling to 65 days from 2028-29, with monthly published performance.

7 Ways to Shorten Your Approval Timeline

1. Lodge a complete application

Incomplete documents are one of the most common causes of delay, because each information request restarts part of the process. See our timeline guide.

2. Design to the controls

A design that meets height, floor space ratio, setbacks and landscaping rules avoids merit debates and variation requests. Variations may also bring back neighbour notification.

3. Check overlays early

Heritage, flooding, bushfire, tree preservation and biodiversity rules can add reports and referrals. Find them before design.

4. Hold a pre-lodgement meeting

Many councils offer them. Ask what your council expects for your type of project.

5. Respond quickly to information requests

Fast, complete responses help keep the file moving.

6. Consider CDC where eligible

It can be faster, but only if your site and design truly meet the standards.

7. Use experienced professionals

A designer, planner and builder who work regularly in your council area know what that council asks for.

What to Budget While You Wait

Approval time is not only a scheduling issue. It affects your budget:

  • Rent or double housing costs while you wait.
  • Interest on the land loan. After the RBA’s rate rise to 4.60% on 29 September 2026, holding costs matter more. See our Q4 2026 decision framework.
  • Consultant fees for updates and responses.
  • Price movements between quote and contract, which can matter if approvals take longer than expected.

For wider budgeting, see hidden costs of a knock down rebuild and knock down rebuild cost in Sydney.

Where to Check Your Own Council

The NSW Planning Portal council league table publishes monthly figures, and your council’s DA tracker shows the progress of individual applications. If your council is at the slower end, plan for the longer program and talk to your designer about CDC and pre-lodgement options.

Pre-Lodgement Checklist

To answer how long does council approval take Sydney owners can control, start with the things that happen before the clock starts:

  • survey, geotechnical report and BASIX completed
  • plans that meet height, floor space ratio, setback and landscaping controls
  • heritage, flooding, bushfire and tree checks done
  • consultant reports attached where required
  • fees ready and the application form complete
  • a neighbour conversation held, even where formal notification is no longer required

A tidy application will not guarantee a fast result, but a messy one almost guarantees a slow one.

Next Steps

Wondering how long does council approval take Sydney owners can expect for your own block? We are happy to talk through your council, site and pathway, with no obligation. See our residential projects and portfolio.

Frequently Asked Questions

Short answers on how long does council approval take Sydney owners ask about most:

How long does council approval take in Sydney in 2026?

It varies by council. The September 2026 league table snapshot shows averages from 41 days in Campbelltown to 122 days in Blacktown, and a statewide average of 84 days as of 31 May 2026.

What is the Government’s target for DA assessment times?

Councils are expected to meet an average of 90 days from lodgement for 2026-27, falling to 80 days in 2027-28 and 65 days from 2028-29, or their previous year’s average if lower.

Are these times for a knock down rebuild specifically?

No. They are averages across all DA types. A well-prepared rebuild application may be quicker or slower than the average.

Does the clock include time waiting for my information?

The league table uses gross days from lodgement to determination, so stop-the-clock periods are not deducted.

Is CDC faster than a DA?

Often, if your site and design qualify. CDC follows fixed standards rather than a council merit assessment. Eligibility depends on your site and local controls.

Where can I see my council’s current performance?

On the NSW Planning Portal’s council league table, which updates monthly, and on your council’s DA tracker.

Related Posts

New home built in Chastwood

Willowie Road Castle Cove

Address: Willowie Road Castle Cove Extensive excavation to “bring the garages to the ground level” and thus the owners no longer need to share their

Clifton Road Clovelly Project 2

Address: Clifton Road Clovelly We’ve turned this Clovelly coastal home into a gorgeous luxury retreat, combining sleek, modern design with expert craftsmanship. From the stunning

Get A Free
Consultation