Building Information Certificate NSW: What Sydney Homeowners Must Check Before a Knock Down Rebuild

Share on

October 19, 2026

A building information certificate NSW homeowners hear about at settlement or at the start of a project is one of the least understood documents in the planning system. People assume it “approves” an old extension. It does not. What it does is narrower, and knowing the difference can save you from a nasty surprise before a knock down rebuild.

This guide explains what a building information certificate (BIC) is, what it protects you from, what it leaves untouched, and the checks to run before you buy or plan a rebuild.

What Is a Building Information Certificate NSW Councils Issue?

A BIC is issued by the local council under Division 6.7 of the Environmental Planning and Assessment Act 1979. It deals with building work that has been carried out without the required approvals. Because a building that has already been erected cannot generally get development consent or a construction certificate after the fact, a BIC is usually the main route to deal with unlawful work.

According to the NSW Planning Portal’s practice note, the council decides whether to issue or refuse it, and applications are lodged through the NSW Planning Portal. Applicants can include:

  • the landowner (or someone with the owner’s consent)
  • a purchaser under a contract for sale, and that purchaser’s solicitor or agent
  • a public authority that has given the landowner notice

You can read the detail in the NSW Planning Portal’s practice note on building information certificates.

What a BIC Does

A BIC means that, from the date it is issued, the council will not take certain compliance actions over the covered work. These include:

  • orders requiring the building to be repaired, demolished, altered, added to or rebuilt
  • civil action relating to encroachment onto council land

It can cover the whole building or part of it. According to the practice note, coverage of unauthorised work does not expire with age, though matters arising only from fair wear and tear are covered for 7 years.

What a BIC Does Not Do

This is where homeowners get caught.

  • It does not approve or legitimise the work. It is not development consent and it is not an occupation certificate.
  • It does not stop fire safety orders or building product rectification orders.
  • It does not prevent proceedings under section 9.50 of the Act for failing to obtain consent or comply with consent conditions.
  • It cannot be amended. If you need changes, you must make a new application.
  • It does not guarantee the work is structurally sound. Councils may ask for engineer’s reports, but a BIC is not a warranty.

A council cannot require an owner to apply for one, but without a BIC, it can still use penalty notices, development control orders (such as stop-work or demolition orders) or prosecution for unauthorised work.

building information certificate nsw

Two-column chart showing what a building information certificate NSW does (stops council orders to repair, demolish or alter covered work, protects against encroachment action) versus what it does not do (approve the work, stop fire safety orders, replace an occupation certificate, guarantee structural soundness)

Timeframes and Appeals

The practice note states the deemed refusal period is 40 days after the application is made, or after the applicant supplies requested information. An appeal must be lodged within 6 months of the council’s decision notice or the end of the deemed refusal period. Councils set their own fees through their published fee schedules, so check your council.

Why This Matters Before a Knock Down Rebuild

If you plan to demolish an existing house, you might think old unapproved work no longer matters. Sometimes it does not, but there are good reasons to check before you commit.

Before you buy. If you are buying a house with the intention of rebuilding, unauthorised work may affect the contract, the settlement and your negotiating position. Buyers and sellers often seek a BIC before settlement to confirm the building will not be subject to council compliance action. A BIC may also be less relevant if the whole building will come down, so ask your solicitor how it applies to your plan.

Before you design. Your approvals, existing-use position, setbacks and floor space calculations may depend on what was lawfully built. If previous work was unlawful, that could affect what council treats as the baseline.

Before you demolish. Unauthorised structures, hazardous materials and services can add cost and complexity. Our demolition cost guide explains the typical items to budget for.

Before you lodge. An unresolved compliance issue can complicate your application, particularly if council identifies unlawful work during assessment.

6 Best Checks Before a Sydney Rebuild

1. Pull the approval history

Check your council’s DA tracker and records for approvals, construction certificates and occupation certificates. Compare them with what is actually on the site: extra rooms, enclosed verandahs, granny flats, studios, pools and sheds.

2. Look for an occupation certificate

A BIC can be issued even where a building lacks an occupation certificate, but the absence is a flag to investigate. Ask why it is missing.

3. Walk the site with a professional

A building inspector or certifier can spot additions that do not appear in the records. This is especially useful on older homes with multiple owners.

4. Check planning controls and certificates

Order a planning certificate for the property to see zoning, heritage, flooding, bushfire and other constraints. These shape your design long before any BIC question arises.

5. Ask your solicitor how a BIC fits the contract

If you are buying, ask whether a BIC should be a condition of the contract and who pays. If you own, ask whether applying makes sense given your plan to demolish.

6. Allow time and budget

A BIC application may require plans, surveys and certificates, and the council has up to 40 days before a deemed refusal. Build this into your program if you decide to apply. See our knock down rebuild timeline for how it fits with design, approvals and demolition.

BIC vs Other Documents: A Quick Guide

DocumentWhat it is
Development consent (DA)Approval to carry out development
Complying development certificate (CDC)Fast-track approval where a project meets set standards
Construction certificateConfirms plans comply with the building code before work starts
Occupation certificateAuthorises occupation after work is completed
Building information certificateDeals with building work carried out without approval; limits certain council actions
Planning certificateLists planning controls affecting the land

Common Mistakes

Thinking a BIC makes old work legal. It limits certain council actions. It is not approval.

Assuming a seller’s “everything is approved” is enough. Check records and the building itself.

Leaving it to the last minute. A BIC, plans and reports take time, and a contract may have a fixed settlement date.

Ignoring it because you will demolish. The decision depends on your timing, contract and risk. Take advice.

Skipping the basics. Many surprises come from unapproved extensions, enclosed outdoor areas and secondary dwellings that were never certified.

What Happens If You Do Nothing?

Without a BIC, council can still act on unauthorised work. The practice note lists penalty notices, development control orders and criminal prosecution among the options. These can bring substantial costs and delays. For a project already under budget pressure, that is a risk worth understanding early. For wider budget considerations, see hidden costs of a knock down rebuild.

When to Get Legal Advice

A building information certificate NSW buyers and owners consider touches property law as well as planning. Speak with a solicitor if:

  • you are buying and the property has additions that do not appear in council records
  • a contract has special conditions about unauthorised work, certificates or settlement dates
  • council has already issued a notice, order or penalty
  • you are unsure whether applying for a BIC helps or complicates your plan to demolish

A certifier or building inspector can help with the building side, but they cannot replace legal advice on contracts and risk.

Next Steps

Not sure whether a building information certificate NSW applies to your property or your rebuild plan? Start with your approval records and a site inspection, and take legal advice before you sign or lodge anything. We are happy to talk through the building side of your rebuild, with no obligation. See our residential projects and portfolio.

Frequently Asked Questions

What is a building information certificate in NSW?

A BIC is issued by a council and deals with building work carried out without the required approvals. It limits certain council compliance actions over the covered work from the date it is issued.

Does a BIC approve unauthorised work?

No. It does not approve or legitimise the work. It means council will not take certain actions, such as orders to demolish or alter, over the covered work.

Can council force me to get a BIC?

According to the practice note, a council cannot require an owner to apply, but it can take action over unauthorised work if no BIC is obtained.

How long does a BIC take?

There is a deemed refusal period of 40 days from the application, or from when requested information is supplied.

Do I need a BIC if I am demolishing the house?

Not necessarily. It depends on your contract, timing and risks. A BIC can still limit orders about the unauthorised work from the issue date, but ask your solicitor how it applies to your plan.

Who can apply for a BIC?

The owner, a purchaser under a contract for sale and their solicitor or agent, and a public authority that has given the owner notice.

Related Posts

Luxury custom home built by a home builder in Mosman

Clifton Road Clovelly Project 1

Address: Clifton Road Clovelly We delivered a major residential rennovation of the residential project at this site, commencing with partial demolition of the original dwelling

Gibbs Street Croydon

Address: Gibbs Street Croydon Construction of a granny flat (2 bed 1 bath), a studio (1 office 1 bath) and a double garage.Construction start to